Material first: define what the system must handle
Different resins and additives behave differently in storage and conveying. A useful design brief describes the material at every stage—from receiving and storage to dosing, blending and delivery at the processing machine.
Record these inputs
- Material name, form and grade
- Bulk density and particle-size range
- Flowability, dust and moisture sensitivity
- Abrasiveness, fragility and contamination limits
- Virgin, regrind, masterbatch and additive ratios

Map the plant layout and conveying path
A clear path map prevents avoidable rework. Start at each material source and trace the route to every receiver, including horizontal distance, vertical lift, bends, junctions and areas that require isolation or routine access.
What the layout should show
- Material storage and pick-up points
- Every receiver, blender and feed throat
- Pipe routes, vertical lift and total distance
- Future machine, storage and mezzanine locations
- Routes reserved for filters and maintenance
Choose the conveying approach from the duty
Vacuum and pressure conveying can both move plastic materials effectively. The correct choice depends on distance, lift, material behavior, source and destination count, cleaning requirements and how the plant will operate.
| System | Best suited to | Points to check |
|---|---|---|
| Vacuum | Multiple receivers, flexible routing and clean indoor production | Filter area, receiver sequencing and vacuum loss |
| Pressure | Longer routes or higher continuous transfer rates | Air quality, heat, pressure rating and discharge control |
| Dense phase | Fragile or abrasive material requiring lower velocity | Material testing and stable feeding conditions |
| Central vacuum | Plants that need shared pumps and automatic distribution | Peak simultaneous demand and redundancy |
Define controls before hardware
Controls determine how the system behaves every shift. Describe the operating rules, visibility and interfaces before final equipment sizing so the control architecture and material routes are designed together.

Size for peak demand—and an agreed expansion plan
Average consumption is not enough. Capacity planning should model the busiest realistic period, machine overlap, material changeovers and the agreed reserve for future lines—not simply an arbitrary oversizing factor.
Capacity planning requires
Give every supplier the same project brief
A comparable quotation starts with comparable inputs. Send each supplier the same factual brief and ask them to state assumptions, exclusions, interfaces and the data used for sizing.
Information to prepare before requesting a proposal
- Plant layout and elevations
- Material list and consumption rates
- Machine and receiver schedule
- Storage and drying strategy
- Controls and integration scope
- Utilities and environmental conditions
- Cleaning and contamination rules
- Expansion plan and acceptance criteria
Compare proposals by decision area
| Area | What should be explicit |
|---|---|
| Design | Selected transport principle, design basis, capacity and redundancy |
| Scope | Included equipment, installation, controls, commissioning and training |
| Interfaces | Electrical, mechanical, utilities, software and owner-supplied work |
| Acceptance | Throughput, cleanliness, alarms, documentation and test procedure |
| Service | Spare parts, remote support, site service and warranty response |